Here's an overview of the construction work underway for the Surgical Services Expansion this week.

DAY WORKS:

  • Staff access corridor will be completed inside day surgery and open to all staff.
  • Construction on link bridge continues through June.
  • Construction of the new orderlies room is underway inside the old gift shop.
  • Construction beginning in stage 1b (old anaesthetic technician’s room) within the perioperative unit. This area will become the theatre operations centre.
  • Demolition of stage 2a areas (old change rooms) within perioperative unit. This area will be the theatre admissions and discharge unit.
  • Steel being installed in basement.

EVENING WORKS (after 5:30pm):

  • Areas of Zacs and the cafĂ© toilets will be blocked off after 5:30pm most nights.
  • Repairs to concrete in stage 2a area within perioperative unit from Thursday.

If you have any questions please email projects@hbdhb.govt.nz.