Works for the surgical expansion project for the week beginning 26 April:

DAY:

  • Construction behind the hoarding in perioperative unit
  • Construction on the link bridge above perioperative and Ruakopito
  • Work in the plant room above surgical unit
  • Reinforcing steel being installed in basement.

NIGHT:

  • Steel being moved into the basement.
  • Scanning and surveying occurring in the perioperative unit.sha

Thank you all for your patience during this work.