Pictured: The bed bays in our new Theatre Admissions and Discharge Unit are getting closer to completion.

Here’s a snapshot of the construction work happening for the Surgical Services Expansion:

  • Ongoing construction continues in the stage 2 area (new Theatre Admissions and Discharge Unit). Vinyl and joinery installation has also started.
  • Construction will continue in the stage five areas (old orderlies office and cleaners store). This work is to convert the area for additional space for the Central Sterile Services Department to house their offices and loan store and is expected to be completed before Christmas.
  • Work will continue on the exterior of the link bridge and in the basement.

Thank you for your patience.