Link bridge

What's happening this week: 09-12 February

The following works are scheduled from Tuesday to Friday this week.

Night works (approx. 7pm – 4am):

Drilling and scabbling (jackhammering) will occur in the basement. 
Day works (approx....

Basement 02022021

What's happening this week: 01-05 February

Thanks to all involved for your continued cooperation with this important construction. The following work will be happening this week:

DAY WORKS (approx. 7am – 5pm)

• Demolition and...

Surgical Expansion Noise digital square generic te reo FINAL

What's happening this week - 18-24 January

The first stages of the surgical services construction are underway.

A big thank you to all staff, patients and whānau for their understanding and patience with the...

Last modified: