New pre and post op area

Works for the week beginning 16 August 2021

Pictured: Construction to build the new pre and post operative unit is underway.

Here's an overview of the construction work this week as we expand our Surgical...

Works for the week beginning 09 August 2021

Construction work underway for the Surgical Services Expansion this week is as follows.

Construction in stage 2a areas (old staff change rooms) within perioperative unit
Construction of the...

Sneak peak link bridge is in its final stages 02082021

Works for the week beginning 2 August 2021

Construction work for the Surgical Services Expansion this week will focus on the following: 

 

Construction in stage 2a areas (old staff change rooms) within perioperative unit
Construction of...

Works for the week beginning 26 July 2021

Here's an overview of the construction work underway for the Surgical Services Expansion this week.

Construction in stage 2a areas (old staff change rooms) within perioperative unit
Construction...

Works for the week beginning 19 July 2021

Here's an overview of the construction work underway for the Surgical Services Expansion this week.

Construction and some noisy work in stage 2a areas (old staff change...

Works for the week beginning 12 July 2021

This week the new perioperative equipment stores opens as part of stage two of the Surgical Services expansion.

Day works:

Demolition and start of construction of the old...

Works for the week beginning 5 July 2021

There will be noise and vibration each night this week from approx 8pm to 3am with work on stage two of the Surgical Services expansion underway....

Works for the week beginning 28 June 2021

Here's an overview of the construction work underway for the Surgical Services Expansion this week.

DAY WORKS:

Construction on link bridge continues through June.
Construction of the new orderlies...